Daesan Biomass Power Plant Cooling Tower, Seosan, South Korea

  • Building type:
  • Energy Construction
Fullscreen map Close

Peikko's first major project in Korea.

 

CGN Company Ltd develops a new biomass power plant in Seosan, about 120 km south from Seoul. Biomass turbine driven compressors with shaft power of 110MW.

Peikko delivered Bolted connections to all the precast in the project's cooling tower building. Peikko's HPKM®/PEC® Column Shoes and HPM®/COPRA® Anchor Bolts were used in the project.

With Peikko systems erection of columns is faster and easier than conventional methods.

 

Project facts

Developer:
CGN DAESAN POWER Co., Ltd.
Construction company:
HYUNDAI ENGINEERING & CONSTRUCTION
Structural Engineer:
BORU, INHUS
Precaster:
TAEHWA Engineering Co., Ltd.
Delivery year:
2019
Completion year:
2021